Audit · Gwanda, Zimbabwe

What Happened to Gwanda Solar Project? How Much Was Paid? When Will Zimbabwe Get the Power?

Zimbabwe's planned 100 MW Gwanda solar station became a prolonged test of procurement, finance and contract management. This audit separates the original US$172.8 million contract from roughly US$5.6–5.7 million in differently classified early payments, the civil judgments and the reported restart. At the 1 October 2026 evidence cut-off, current financial close and physical delivery remained unverified in the material reviewed.

· Updated 15 October 2026

Watch the audit

Open on YouTube ↗

The audit question

What happened to Gwanda's promised 100 MW solar station, what did the early payments and court judgments establish, and what evidence would verify delivery of electricity?

Zimbabwe signed a contract for a 100-megawatt solar power station at Gwanda in 2015. By the audit's evidence cut-off of 1 October 2026, a reported instruction to proceed had returned the project to public attention. The central question was whether the contract, early spending and subsequent court victories had become a functioning electricity asset.

The record supports a qualified answer. Public money paid for feasibility and preliminary work, and the civil courts recognised that some value had been delivered. The amended contract survived litigation and specific performance was ordered. A later restart was reported. But the evidence obtained for the audit did not verify current financial close or current physical delivery at the site.

Understanding that conclusion requires keeping six things separate: the contract price, money actually paid, work delivered, legal rights, financing and electricity generated. A figure in one category cannot stand in for evidence in another.

Why Gwanda mattered to Zimbabwe's electricity system

The project was commissioned into an electricity shortage. Reduced water availability at Kariba constrained hydroelectric generation, while ageing thermal equipment limited dependable output. The African Development Bank's 2019 report, drawing on ZETDC data, recorded a 2015 supply deficit of about 515 megawatts at peak demand. Imports supplemented domestic generation, and load-shedding was one response when supply could not meet demand.

A completed 100-megawatt solar station would therefore have offered material additional generation and diversification in a system heavily dependent on coal and hydropower. It would not have ended the national shortage by itself. Installed solar capacity is not continuous output throughout every hour of the day, and the promised capacity was never proof of electricity already delivered.

The significance of delay extended beyond the payment ledger. Zimbabwe went without the potential generation and diversification that the completed project was intended to provide. For households and businesses, the relevant end product was a commissioned station supplying the grid.

The contract and the procurement route

Zimbabwe Power Company, or ZPC, was the project owner and contractual employer. Intratrek Zimbabwe was the contractor. CHINT was Intratrek's partner, presented in the court record as possessing technical and financial capacity and participating in the financing effort. ZPC was the intended borrower, while Intratrek was expected to facilitate financing and deliver the engineering, procurement and construction project.

The agreement signed on 23 October 2015 carried a price of about US$172.8 million, excluding taxes. That was the price of the power station under the original contract. It was not the amount paid to Intratrek.

Parliament's committee account places the first tender advertisement in June 2013 and an initial award to China Jiangxi in January 2014. That procurement was subsequently cancelled. A later process in 2015 produced the Intratrek contract. References to the earlier winner and to Intratrek as the lowest compliant bidder therefore concern different procurement rounds.

The committee criticised negotiations over bids, contractor vetting and safeguards. Intratrek defended its offer's technical merits, and ZPC described it as the lowest compliant bidder in the later procurement. The audit did not obtain the complete evaluation scores and bid schedules needed to independently settle that selection argument. Those missing records prevent a definitive reconstruction; they do not justify inventing motives for officials or bidders.

Signing was not the construction start

The contract set conditions to be met before the main works commenced. Financing agreements had to become effective, with initial drawdown conditions satisfied. The arrangements also called for an advance-payment guarantee, performance security and receipt of the advance. Other requirements included a bankable feasibility study, environmental approval, land acquisition, employer due diligence and corporate authorisations. Delivery depended on obligations on both sides.

There were two distinct clocks. The original period for satisfying the conditions was 24 months after signature. Construction was to take 540 calendar days from the contractual commencement date. Counting those 540 days from signature would erase the distinction. Later extensions, amendments and the parties' conduct became central to the dispute about whether the agreement had ended.

Preliminary work could nevertheless proceed before full commencement. Studies, site clearance and temporary facilities could be undertaken while financing and construction arrangements remained unresolved. This explains how spending and some work could occur without delivery of a generating station. It also explains why a site photograph cannot account for every category of expenditure.

What the early payment records establish

The public accounts do not produce a single reconciled payment schedule. In the Supreme Court record, ZPC described an advance of about US$5.6 million. The record referred to about US$2.3 million associated with feasibility work and about US$3.3 million that later survived as ZPC's refund counterclaim.

The litigation record separately described an addendum budget of about US$5.1 million for pre-commencement works, excluding taxes and feasibility costs, a contractor contribution of about US$1 million and an asserted outstanding amount of about US$1.2 million. These categories must not be added together as though each were a separate cash advance.

ZPC's later public account differed. In May 2024, it described about US$5.7 million as having been advanced, comprising roughly US$2.1 million for feasibility, about US$2.8 million for other pre-commencement works, plus value-added tax.

The figures refer to the same broad early-spending period, but their totals and classifications are not identical. Complete payment schedules, vouchers, bank records and tax reconciliation are needed before one precise breakdown can be presented as settled. Parliament, the litigation record and later ZPC reporting leave an accounting discrepancy to resolve. The discrepancy alone is not evidence that a difference was stolen.

A budget is not necessarily cash paid. Feasibility may sit inside one total and outside another, while taxes may be included or excluded. A valuation of delivered work answers a different question again: it does not trace every payment through the recipient's accounts.

Work delivered, dated observations and the fence dispute

The civil record recognises feasibility work and some site work. The court rejected the blanket claim that preliminary payments produced no value. That does not settle the quantity, quality or present usefulness of each deliverable.

Parliament's 2018 visit described limited preparatory development. CITE's reporting of a parliamentary visit in May 2024 described a neglected site, vegetation and deteriorating temporary structures, without the promised power station. The latest substantive site observation obtained for this audit was from May 2024. It cannot be represented as an inspection in October 2026.

The fence illustrates an unresolved evidentiary conflict. The Supreme Court record describes the parties as agreeing after a July 2020 joint inspection that the fence had been erected and completed. Later ZPC reporting described access-road work, fencing and signage as partially complete after a joint inspection in 2020. The accounts are in tension, but the available sources do not establish whether they describe the same inspection and scope. Different inspection dates should not be invented to reconcile them. The signed reports and annexures are needed to resolve the difference.

The September 2017 addendum named subcontractors and work periods and recorded about US$1.2 million still to be paid for preliminary activities. It also acknowledged that the required advance-payment guarantee for money already released remained outstanding. Payment obligations and safeguards were both unresolved.

What the civil courts decided

ZPC argued that the conditions had not been fulfilled and that the agreement had expired or could be terminated. Intratrek argued that ZPC had failed to pay subcontractors and obstructed financing arrangements. These were competing positions; the later judgments tested them against the agreement and evidence.

Intratrek obtained a High Court order in 2018. In 2021, the Supreme Court set that decision aside because material factual disputes required a trial. That procedural reversal was not a final ruling that ZPC had lawfully ended the contract.

Following trial, the High Court held in January 2023 that the amended contract remained valid and binding. It ordered specific performance and dismissed ZPC's counterclaim. On 1 December 2023, the Supreme Court dismissed ZPC's appeal. An account that stops at the 2021 reversal leaves out the eventual contractual outcome, which favoured Intratrek.

The courts treated the addendum as part of the contract. Its new periods for preliminary work extended beyond the original conditions deadline, and the parties' conduct was inconsistent with automatic termination on that earlier date. The judgments also found that ZPC had frustrated completion of the financing arrangements. ZPC could not rely on non-fulfilment it had itself frustrated to escape the contract.

The judgments applied fictional fulfilment, treating the obstructed financing condition as fulfilled against the party that prevented it. That legal treatment supported enforcement of the contract. The court also accepted evidence concerning funding for an initial 10-megawatt phase. Neither that historical finding nor fictional fulfilment establishes full-project financial close or the availability of funds at the 1 October 2026 cut-off.

Performance was the remedy, not a US$22 million payout

Specific performance required the parties to carry out their contractual obligations. It was not an award of US$22 million to Intratrek. The company's alternative damages claim was US$25 million, including about US$3 million in expenses and US$22 million in expected profit. The court granted performance rather than those alternative damages. Claimed damages must not be reported as money awarded or paid.

ZPC's surviving refund claim of about US$3.3 million also failed after broader claims had been narrowed. That result followed the findings about the continuing contract and preliminary work. It was not a forensic certificate that every dollar had been properly spent. Equally, non-completion of the whole station did not automatically make every preliminary payment recoverable in that civil case.

Oversight findings still needed follow-through

Parliament examined procurement, guarantees and monitoring. The Auditor-General's report for 2017 raised a performance concern about preliminary works. Its payment figure was not reconciled with the court-recorded figures and should not be added as another separate amount.

A parliamentary report in 2024 recommended stronger due diligence, clear performance indicators and effective dispute resolution. In Parliament in April 2025, the Energy Ministry acknowledged past contract-management shortcomings. Recognition of a problem and recommendations to fix it do not prove that the controls were implemented and tested. That requires separate evidence.

What the reported restart did and did not prove

Reporting in March 2025 described a joint review of price, technology, feasibility and grid connection. Zimpapers subsequently reported a restated engineering, procurement and construction agreement dated 27 March 2025, with a price of US$132 million. The audit did not obtain the signed restatement, so that date and price remain attributed to the reporting.

The lower headline price cannot be treated as a verified saving. The original price excluded taxes. A like-for-like comparison would need matching equipment, project scope, financing charges, grid works and the treatment of earlier expenditure. Until the schedules are compared, the saving is unestablished.

Reports published by Zimpapers and newZWire on 10 September 2026 described a Notice to Proceed and a 24-month execution period. The publication date was not an authenticated contractual starting date. Without the notice, its effective date and the agreed programme, the reports do not establish a binding September 2028 completion deadline.

The same reporting described an advance still to be released. Intratrek said a required guarantee had been submitted through its partner and announced mobilisation of personnel, equipment and temporary facilities. Those statements are distinct from ZPC confirming acceptance of the security, evidence of payment, or an engineer certifying completed works.

An advance-payment guarantee provides security for the owner. It is not the advance itself and does not establish full project financial close. At the audit cut-off, financial close remained unverified in the available evidence. Unverified financing is not the same as proven financing failure.

A changed national system, but continuing value in delivery

Zimbabwe's electricity system had changed materially since 2015. The Hwange expansion brought two new units into service in 2023, adding about 600 megawatts. ZERA's 2024 annual report attributed a decline in reported external electricity supply, from roughly 2,000 gigawatt-hours in 2023 to about 1,250 in 2024, to commissioning Hwange 7 and 8. Its 2024 supply table includes exports as negative entries. These are the regulator's reported external-supply figures, not an independently reconciled gross-import series.

A September 2026 analysis by the Zimbabwe Environmental Law Organisation, citing a ZESA weekly update for the week ending 29 May, reported 161 consecutive days without load-shedding. It also reported local generation of about 1,950 megawatts and imports of about 190 megawatts, with supply after exports exceeding forecast evening demand. The analysis labels its detailed supply balance and generation snapshot 31 May. These were dated operating figures, not a guarantee of permanently available capacity.

Zimbabwe's 2025 National Energy Compact put ZPC's dependable generating capacity at roughly 1,200–1,600 megawatts against national peak demand of about 2,000 megawatts. Although installed capacity exceeded peak demand on paper, constrained dependable capacity continued to require imports and load-shedding for system stability. Plant availability, hydro conditions and imports can change, so a strong operating week cannot replace an assessment of dependable capacity.

The system had improved, but its capacity margin remained thin. Additional functioning solar generation could provide another source of supply and diversify a mix dominated by coal and large hydropower. Gwanda did not need to solve the whole national shortage to matter. It needed to become a working asset.

The evidence that should decide the next announcement

Future claims about Gwanda should be tested along three connected lines:

  • Obligation: Identify the operative agreement, responsibilities, effective start date and dated construction programme. Explain any changed milestones against the previous commitment
  • Funding: Establish what advance was actually paid, which security ZPC accepted, and what finance is committed and available for the next stages
  • Physical delivery: Identify this particular project site, record installed and usable work, connect certified progress to the programme, and ultimately verify commissioning, grid connection and measured output

Photographs of another solar installation in the Gwanda area cannot establish this project's delivery. A feasibility study may be necessary, and preliminary works may be legitimate, but neither supplies electricity. A court order can preserve an obligation without financing, building or commissioning the station.

Hwange provides an important domestic comparison. Zimbabwe has completed major generating assets. The useful institutional question is why one project reached operation while another became caught in procurement, finance, litigation and contract management. Treating failure as inevitable obscures the delivery mechanisms that need examination.

The Kopje Journal & Review's conclusion, at the 1 October 2026 cut-off, is that Gwanda must be judged by a verifiable path from contractual obligation through funding to functioning infrastructure. The record establishes early feasibility and preliminary spending, an enforceable amended contract, acknowledged management problems and a reported restart. It does not yet establish current financial close or current physical delivery in the evidence reviewed. The ultimate public test is what was paid for, what was delivered and whether people can use it.

Evidence & accountability

Sources & editorial status

  1. Intratrek Zimbabwe (Private) Limited v Zimbabwe Power Company (Private) Limited — HH13-23, HC2337/21 ↗Primary document · 11 January 2023
  2. Zimbabwe Power Company v Intratrek Zimbabwe — SC127/23, Civil Appeal SC38/23; [2023] ZWSC56 ↗Primary document · 1 December 2023
  3. Zimbabwe Power Company v Intratrek Zimbabwe — SC39/21, SC2/19 ↗Primary document · 10 May 2021
  4. Parliament’s full report on the Chivayo Gwanda solar project ↗Primary document · 3 June 2018
  5. Stalled Gwanda solar project raises concerns: Parly visit exposes lack of progress ↗Credible reporting · 23 May 2024
  6. Intratrek Zimbabwe v Zimbabwe Power Company — HH818-18, HC8159/18 ↗Primary document · 13 December 2018
  7. Report of the Auditor-General for the year ended 31 December 2017 on State Enterprises and Parastatals ↗Primary document · 12 June 2018
  8. Report of the Portfolio Committee on Energy and Power Development on the State of Electricity Supply in Zimbabwe — SC02 ↗Primary document
  9. National Assembly Hansard — Volume 51 Number 41 ↗Primary document · 3 April 2025
  10. Gwanda Solar Project resumes under new terms ↗Credible reporting · 24 March 2025
  11. Gwanda Solar Project revived ↗Credible reporting · 10 September 2026
  12. Gwanda Solar: Chivayo given 24 months to pull his weight on stalled project ↗Credible reporting · 10 September 2026
  13. Gwanda Solar Project: ZPC cites funding hurdle, defends contractor selection — CITE ↗Credible reporting · 23 May 2024
  14. Zimbabwe Infrastructure Report 2019 — African Development Bank ↗Primary document
  15. ZERA 2024 Annual Report ↗Primary document
  16. National Energy Compact for the Republic of Zimbabwe — Mission 300 ↗Primary document · 8 October 2025
  17. Zimbabwe Half Year Electricity Situation — Zimbabwe Environmental Law Organisation ↗Credible reporting · 14 September 2026
Source note

Evidence cut-off: 1 October 2026. The latest substantive site observation obtained for the audit was from May 2024; it does not establish the site condition at the cut-off. The original contract is reconstructed through court records. The signed restated agreement, complete Notice to Proceed, current financial close, current inspection and fully reconciled payment ledger were not verified in the source material. The May 2026 electricity figures describe a dated operating snapshot, not a permanent capacity guarantee. The May operating figures were read through the Zimbabwe Environmental Law Organisation’s September 2026 analysis of a ZESA report; the analysis refers to a week ending 29 May and labels detailed snapshots 31 May. The ZERA annual figures are reported external-supply totals; the source tables should not be treated as independently reconciled gross imports.

Send a correction or source ↗

Cookie choices

You can read every audit with optional media switched off. Your choice applies to this browser for up to 180 days.

Essential website functions

Security, Publisher sign-in and remembering your privacy choice.

Always active

No KJR advertising or analytics tags run on this version of the website. Social links and Stripe checkout open only when you follow a link.

Cookie policy · Privacy statement · European & UK rights